[TO BE PUBLISHED IN
THE GAZETTE OF INDIA, EXTRAORDINARY, PART II, SECTION 3, SUB-SECTION (i)]
GOVERNMENT
OF INDIA
MINISTRY
OF FINANCE
(DEPARTMENT
OF REVENUE)
New
Delhi, the 10th September, 2012
Notification No. 34 /
2012 - Central Excise
G.S.R. (E).- In exercise of the
powers conferred by sub-section (1) of section 5A of the Central Excise Act,
1944 (1 of 1944), the Central Government, on being satisfied that it is
necessary in the public interest so to do, hereby makes the following further
amendments in the notification of the Government of India, in the Ministry of
Finance (Department of Revenue), No. 12/2012-Central Excise, dated the 17th
March, 2012, published in the Gazette of India, Extraordinary, Part II, Section
3, Sub-section (i), vide number G.S.R. 163(E), dated the 17th March, 2012,
namely:-
In the said notification, -
(A) in the Table,
(i) against Sl. No. 337, in the
entries under column (3), for the words “required for setting up of an
ultra-mega power project”, the words and figures “required for setting up of an
ultra-mega power project specified in List 10,” shall
be substituted;
(ii) against S. No. 338, in the
entries under column (3), for the words “supplied to mega power projects”, the
words and figures “supplied to mega power projects specified in List 11,” shall be substituted;
(iii) against S. No. 339, in the entries under column
(3), for the words “expansion of an existing mega power project so certified”,
the words, figures and symbols “expansion of mega power projects, namely, Vindhyachal STPP Stage-V (Expansion Unit) - 500 MW (NTPC)
and UNOSUGEN CCPP, Gujarat (An expansion unit of Sugen
CCPP of 1147.5 MW)- 382.5(1) MW (M/s. Torrent Power Ltd.) so certified before
the 19th day of July, 2012” shall be substituted;
(B) in
the ANNEXURE,
(i) in the Condition No.
42, in clause (a), after the words “mega power project”, the words “before the
19th day of July, 2012” shall be inserted;
(ii) in the Condition No. 43, in clause (a), after the words “Mega
Power Project”, the words “before the 19th day of July, 2012” shall
be inserted;
(iii) after List 9 and the
entries relating thereto, the following Lists and entries shall be inserted,
namely:-
“List 10
(See S. No. 337 of the Table)
1 Krishnapatnam UMPP, Andhra
Pradesh- 6x660= 3960 MW (Coastal Andhra Power Ltd.)
2 Mundra UMPP, Gujarat-
5x800= 4000 MW (Coastal Gujarat Power Ltd.)
3 Sasan, Madhya Pradesh-
6x660= 3960 MW (Sasan Power Ltd.)
4 Tilaiya UMPP, Jharkhand-
5x800= 4000 MW (Jharkhand Integrated Power Ltd.)
5 Orissa UMPP, Orissa- 5x800= 4000 MW
6 Chhattisgarh UMPP, Chhattisgarh-
5x800= 4000 MW
7 Cheyyur UMPP,- 5x800= 4000MW
List 11
(See S. No. 338 of the Table)
1 Parbati-II, Himachal Pradesh - 4x200=800 MW (NHPC)
2 Teesta- V, Sikkim - 3x170=510 MW (NHPC)
3 Sipat-II, Chhattisgarh - 2x500=1000 MW (NTPC)
4 Vindhyachal-III, Madhya Pradesh - 2x500=1000 MW (NTPC)
5 Talcher-II, Orissa - 4x500=2000 MW (NTPC)
6 Rihand-II, Uttar Pradesh - 2x500=1000 MW (NTPC)
7 Sipat-I, Chhattisgarh - 3x660=1980 MW (NTPC)
8 Kahalgaon-II Phase-I & II Bihar - 3x500=1500 MW (NTPC)
9 Barh, Bihar - 3x660=1980 MW (NTPC)
10 Koldam, Himachal Pradesh - 4x200=800 MW (NTPC)
11 Tuticorin,
Tamil Nadu- 2x500=1000 MW (NLC)
12 Parbati-III, Himachal Pradesh - 4x130=520 MW (NHPC)
13 Jhanor Gandhar CCPP-II, Gujarat -
2x650=1300 MW (NTPC)
14 Kawas CCPP-II, Gujarat - 2x650=1300 MW (NTPC)
15 RGPPL,
Maharashtra - 2150 MW (JV of NTPC/ GAIL/ Govt. of Maharashtra)
16 Tapovan Vishnugad HEP, Himachal
Pradesh - 4x130=520 MW (NTPC)
17 Simhadri-II, Andhra Pradesh - 2x500=1000 MW (NTPC)
18 Indira Gandhi STPP-JV project, Haryana - 3x500=1500 MW
(NTPC)
19 Bongaigaon, Assam - 3x250=750 MW (NTPC)
20 Barh-II, Bihar - 1320 MW (NTPC)
21 Koderma TPS St-I, Jharkhand – 1000 MW (DVC)
22 Durgapur
Steel TPS, West Bengal - 2x500=1000 MW (DVC)
23 Tehri Pump Storage Project – 4x250=1000 MW (THDC)
24 Mauda, Maharashtra – 2x500=1000 MW (NTPC)
25 Rihand- III, Uttar Pradesh - 2 x 500=1000 MW (NTPC)
26 Nabinagar- JV with Railways, Bihar - 4 x 250=1000 MW (NTPC)
27 Vallur Stage- I Phase I & II, Tamil Nadu - 3 x 500=1500
MW (NTPC-Tamil Nadu Energy Co. Ltd.)
28 Raghunathpur TPS
Phase 1, West Bengal - 2 x 600=1200 MW (DVC)
29 Tanda- II, Uttar Pradesh-2 x 660=1320 MW (NTPC)
30 Meja, Uttar Pradesh - 2 x 660=1320 MW (NTPC)
31 Vindhyachal-IV, Madhya Pradesh - 2 x 500=1000 MW (NTPC)
32 Solapur STPP, Maharashtra - 2x660=1320 MW (NTPC)
33 Nabinagar STPP, JV with Bihar, Bihar-3x660=1980 MW (NTPC)
34 Mouda STPP-II, Maharashtra- 2x660= 1320 MW (NTPC)
35 Raghunathpur TPS (Ph-II), West Bengal- 2x660=1320 MW (DVC)
36 North
Karanpura STPP, Jharkhand- 3x660=1980 MW (NTPC)
37 Kudgi STPP stage-I, Karnataka- 3x800=2400 MW (NTPC)
38 Darlipalli STPP, Stage-I, Orissa- 2x800=1600 MW (NTPC)
39 Barethi STPP, Madhya Pradesh- 6x660=3960 MW (NTPC)
40 Lara
STPP, Chhattisgarh -2x800=1600 MW (NTPC)
41 Gajmara STPP Stage-I - 2x800= 1600MW (NTPC)
42 Rajiv
Gandhi CCPP Stage- II
Phase-I, Kerala- 3x350 =1050 MW (NTPC)
43 Gidderbha STPP, Punjab - 4x660= 2640 MW (NTPC)
44 Khargone Super TPP, M.P. - 2x660= 1320 MW (NTPC)
45 Gadarwara Super TPP, M.P. - 2x660= 1320 MW (NTPC)
46 Katwa Super TPP, West Bengal - 2x800= 1600 MW (NTPC)
47 Bilhapur STPP, Uttar Pradesh -2x660= 1320 MW (NTPC)
48 Talcher STPP Stage-III, Orissa - 2x660=1320 MW (NTPC)
49 Khedar (Hissar), Haryana - 1000
(+200) MW (HPGCL)
50 Khandwa, Madhya Pradesh - 2x500= 1000 MW (MPPGCL)
51 Gas
based CCPP Pragati-III, Delhi-1371.6 MW (Pragati Power Corp. Ltd.)
52 Sri Damodaran Sanjeevaiah, Nellaturu, Andhra Pradesh - 2x800=1600 MW (APPDCL)
53 Chandrapur Expansion, Maharashtra- 2x500= 1000 MW (MSPGCL)
54 Koradi Expansion, Maharashtra- 3x660= 1980 MW (MSPGCL)
55 Bhusawal Expansion, Maharashtra- 2x500= 1000 MW (MSPGCL)
56 Supercritical
TPP at STPS Stage-V at Suratgarh, Rajasthan- 2x660)= 1320 MW (RRVUNL)
57 Supercritical
TPP at Chhabra, Rajasthan - 2x660= 1320 MW (RRVUNL)
58 North
Chennai, Tamil Nadu-2x600=1200 MW (TNEB)
59 Purulia Pump Storage Hydel
Project, West Bengal- 4x225= 900 MW (State Sector)
60 Sagardighi TPP Ext. Unit 3&4, West Bengal-2x500=1000 MW
(WBPDCL)
61 Shree
Singaji TPP-2x660 (MP Power Generating Company Ltd MW
(MPPGCL)
62 Raigarh TPP, Chhattisgarh- 4x250= 1000 MW (M/s. Jindal Power Ltd.)
63 Akhakhol GBPP, Gujarat- 3x382.5= 1147.5 MW (M/s. Jindal Power Ltd.)
64 Udupi (Nagarjuna) Power Project,
Karnataka- 2x600= 1200 MW (M/s. Udupi (Nagarjuna) Power Corp. Ltd.)
65 IPP
project Haryana- 2x660= 1320 MW (M/s. Jhajjar Power
Ltd.)
66 726
MW CCGT being developed by ONGC-Tripura Power Company Ltd. (OTPC) at Palatana, Tripura - (2x250)(2x113.3)=
726 MW
67 Salaya TPP, Gujarat- 2x600= 1200 MW (M/s. Essar Power Gujarat Ltd.)
68 Tiroda TPP, Maharashtra-5x660=3300 MW (M/s. Adani Power Maharashtra Ltd.)
69 Kawai
TPP, Rajashtan - 2x660=1320 MW (M/s. Adani Power Rajasthan Ltd.)
70 Teesta-VI, Sikkim - 4x125= 500 MW (M/s. Lanco)
71 Teesta-III Sikkim- 6x200= 1200 MW (M/s. Teesta
Urja Ltd.)
72 KSK
Mahanadi Power Company Ltd.(U-3 & 4) Janjgir- Champa,
Chhathisgarh-2x600=1200 MW (M/s KSK Mahanadi Power Co Ltd.)
73 Rajpura TPP in the State of Punjab- 2x700= 1400 MW (M/s. Nabha Power Ltd.)
74 Talwandi Sabo power project at Banawala,
Punjab.- 3x660=1980 MW (M/s. Talwandi
Sabo Power Ltd. (TSPL))
75 TPP
at Nandgaonpeth, MIDC, Amravati Dist,. Maharashtra.- 5x270= 1350 MW
(M/s. Indiabulls Power Ltd.)
76 TPP
at Karachhana, Allahabad, UP- 2x660 = 1320 MW (M/s. Sangam Power Gen Company Ltd.)
77 TPP
at Bara, Allahabad, UP. - 3x660=1980 MW (M/s. Prayagraj
Power Gen. Company Ltd.)
78 TPP
at Surguja, Chhattisgarh- 2x660 = 1320 MW (M/s. IFFCO
Chhattisgarh Power Ltd.)
79 TPP
at Dhenkanal, Orissa- 3x350=1050 MW (M/s. GMR Kamalanga Energy Ltd.)
80 GMR Chhattishgarh Energy Ltd. Raipur, Chhattisgarh- 2x685 MW
81 KSK
Mahanadi Power Corporation Ltd. (U-2&5) Janjgir Champa, Chhattisgarh- 2x600 MW
82 KSK
Mahanadi Power Corporation Ltd. (U-1&6) Janjgir Champa, Chhattisgarh- 2x600 MW
83 Thermal
Powertech Corporation Ltd. Pynampuram
Andhra Pradesh- 2x660 MW
84 KVK Neelanchal Power Pvt. Ltd Cuttak,
Orissa- 3x350 MW
85 East-Coast
Energy Pvt. Ltd Srikakulam, Andhra Pradesh.- 2x660 MW
86 Monnet
Power Corporation Ltd. Malibrahmani, Orissa- 2x525 MW
87 Hinduja National Power Corporation Ltd. Vishakhapatnam,
Andhra Pradesh- 2x520 MW
88 Corporate
Power Ltd. Chandwa, Jharkhand- 4x270 MW
89 Lanco Power Ltd.
(U-3,4) Pathadi,
Chhattisgarh- 2x660 MW
90 Lalitpur Power
Generation Company Ltd. Lalitpur, U.P.- 3x660 MW
91 Lanco Vidarbha Thermal Power Ltd. Wardha,
Maharashtra- 2x660 MW
92 Lanco Babandh Power Ltd. Dhenkanal,
Orissa- 2x660 MW
93 DB Power Ltd. Vadodarha
TPP Janjgir – Champa Chattisgarh- 2x660 MW
94 Athena Chhattisgarh Power Ltd. Singhitarai TPS Janjgir-Champa, Chattisgarh- 2x600 MW
95 Essar Power
Jharkhand Ltd. Tori, Jharkhand- 2x600 MW
96 MB Power (MP) Ltd. Anuppur, Madhya Pradesh-
2x600 MW
97 RKM Powergen Pvt.
Ltd. Uchpinde TPP Janjgir- Champa, Chattisgarh- 4x360 MW
98 IL & FS Tamil Nadu Power Company Ltd. Cuddalore, Tamil Nadu- 2x600 MW
99 Meenakshi Energy
Pvt. Ltd Thamminapatanam, Andhra Pradesh-Ph-1:2x 150 Ph-II 2x350 MW
100 SKS Power Generation (Chhattisgarh) Ltd. Binj Kote TPP Raigarh,
Chhattisgarh- 4x300 MW
101 Jindal India
Thermal Power Ltd. Angul, Orissa- 2x600 MW
102 NCC
Power Projects Nellore AP- 2x660 MW
103 Samalkot Power Ltd.
Samalkot, Andhra Pradesh- 2400 MW
104 Torrent Energy Ltd. Dahej,
Gujarat- 1200 MW”.
[F.No. 354/78/2010-TRU(Pt-1)]
(Rajkumar
Digvijay)
Under Secretary to
the Government of India
Note: The principal
notification No. 12/2012-Central
Excise, dated the 17th March, 2012, was published in the Gazette of India, Extraordinary, Part II,
Section 3, Sub-section (i), vide number G.S.R.
163(E), dated the 17th March, 2012 and was last amended vide notification No. 28/2012-Central Excise,
dated the 27th June, 2012, published vide number G.S.R. 509(E),
dated the 27th June, 2012.